How Many Solar Panels Do I Need?
Last updated: · 2 min read
The first question in sizing a solar system is how many panels. The tool uses daily consumption, peak sun hours and efficiency to find panel count, installed power, area and inverter, and the battery for off-grid systems.
Formula
Required power = daily kWh ÷ (sun hours × efficiency) Panels = round up(power ÷ panel) Battery = daily kWh × days ÷ (V × DoD)
Efficiency covers temperature, wiring, dirt and inverter losses; sun hours are the yearly average of your site.
What the inputs mean
- Daily consumption
- Average daily use.
- Peak sun hours
- Yearly average sun hours.
- System efficiency
- System efficiency, usually 75–82%.
- Panel power
- Panel power.
- Panel area
- Panel area.
- Peak load
- Largest simultaneous load.
- Battery autonomy (0: grid-tied)
- Days of battery autonomy; 0 for grid-tied.
Worked example: 10 kWh a day, 4.5 hours, 78%, 550 W panels
- Required: 10 ÷ (4.5 × 0.78) = 2.85 kW.
- Panels: 2,849 ÷ 550 → 6; installed 3.3 kWp.
- Area 15.6 m²; yearly output 4,227.8 kWh.
Result: 6 panels produce about 4,227.8 kWh a year.
☀️ Solar System Sizing Calculator
Free, no sign-up; your data stays in your browser.
Open the calculator →Also in this calculator
- Compare: up to three results side by side, with differences in amount and percent
- Chart: how the result moves when one value changes
- Download Excel: inputs, result and the table if there is one
- Save: keep the calculation in your own browser only
How to read the result
For preliminary sizing only; a qualified engineer must check the design and protection. Use PVGIS or PVWatts for tilt, direction and shade.
Common mistakes
- Using the yearly average for an off-grid winter.
- Ignoring shade.
- Choosing an inverter equal to panel power.
Frequently asked questions
Where do I find sun hours?
PVGIS or your national solar map.
Do I need a battery?
Not with net metering; batteries are for outages and off-grid.
Will my roof fit?
Add about 20% to the panel area.
The result is not exact or binding and is for information only; it is not an official document and cannot be used in official procedures. Confirm it with the competent authority or a professional before acting; no liability is accepted for losses arising from its use.