Short-Circuit Current: Transformer and Cable
Last updated: · 2 min read
To choose a breaker you need the largest short-circuit current at that point. The tool estimates the current at the transformer from its rating and uk and at the cable end from length and section, plus the peak value.
Formula
Zt = uk × U² ÷ S Ik = U ÷ (√3 × √(R² + (Xt + Xk)²)) ip = κ × √2 × Ik
The grid is taken as infinite, the transformer as purely inductive, cable reactance as 0.08 mΩ/m and voltage factor 1.
What the inputs mean
- Transformer rating
- Transformer rating.
- Impedance voltage (uk)
- Impedance voltage on the nameplate.
- Secondary voltage
- Secondary line voltage.
- Cable length
- Cable length to the point.
- Cable section (per phase)
- Section per phase.
- Conductor
- Copper or aluminium.
Worked example: 630 kVA, uk 4%, 400 V, 20 m of 150 mm² copper
- Transformer impedance 10.16 mΩ; at the terminals 22.73 kA.
- Cable resistance 2.47 mΩ.
- At the cable end 19.22 kA; peak 41.92 kA.
Result: The breaker here needs a breaking capacity of at least 19.22 kA.
🧨 Short-Circuit Current Calculator
Free, no sign-up; your data stays in your browser.
Open the calculator →Also in this calculator
- Compare: up to three results side by side, with differences in amount and percent
- Chart: how the result moves when one value changes
- Download Excel: inputs, result and the table if there is one
- Save: keep the calculation in your own browser only
How to read the result
For preliminary sizing only; a qualified engineer must check the design and protection. Motor contribution and hot cable resistance are ignored; use IEC 60909 for a full study.
Common mistakes
- Entering a return length.
- Typing uk as a decimal.
- Treating the result as a trip setting.
Frequently asked questions
Minimum short-circuit current?
That needs phase-neutral impedance; this gives the maximum.
Unknown grid power?
An infinite grid gives the largest current.
Parallel cables?
Multiply the section.
The result is not exact or binding and is for information only; it is not an official document and cannot be used in official procedures. Confirm it with the competent authority or a professional before acting; no liability is accepted for losses arising from its use.